Unit 2's reactor support ring is in place — a major step as we continue towards our second dome lift.
#BuiltByUs
Posts by Hinkley Point C
Meet Stanley.
One of the 1,500 apprentices at Hinkley Point C, part of the 26,000 across Britain helping to build the new power station.
The 2025 Socio-Economic Report highlights the project's boost to Britain's growth and the South West's economy.
Learn more: edfenergy.com/hpc-benefits
We’ve completed our third mega cage lift, hoisting 170 tonnes of rebar onto unit 2’s reactor building – the biggest single lift of rebar yet.
This achievement highlights the power of modular construction, ensuring safer, higher quality, and faster builds.
#BuiltByUs
Watch the first weld in the reactor building on unit 1’s primary circuit. This work will connect together the reactor pressure vessel (RPV), four steam generators and the four main coolant pumps. The welds will be some of the most complex and critical on our project.
#BuiltByUs