Video

CONSTRUCTION UPDATE: The Avenue 17 Grade Separation in Madera County will improve east to west mobility! 🀝

Once a dead end, the grade separation will allow vehicular traffic to travel along Ave 17β€―from Lake St.β€―to Raymond Rd, over the existing freight & future HSR tracks.πŸš„πŸ’¨

#BuildCA #BuildHSR

17 3 0 1
Video

Construction Update: The Avenue 88 Grade Separation in Tulare County is close to completion! βœ…

The overpass is ready to be paved & striped! When complete, the grade separation will take traffic over State Route 43, the BNSF & future HSR tracks. πŸš„πŸ’¨

#BuildCA #BuildHSR

30 2 0 0
Video

Construction Update: Tulare Street Underpass | πŸ“ Fresno, CA

Progress is being made everyday in downtown Fresno! The high-speed rail bridge is continuing to take shape with concrete placed for the sidewalks and new streetlights installed!

Learn more at buildhsr.com! #BuildCA #BuildHSR

25 3 0 0
Video

CONSTRUCTION UPDATE: Tulare Street Underpass |πŸ“Fresno County

πŸ› Crews have tied rebar & poured concrete
βœ…Mass excavation for the underpass completed
πŸ—All 14 girders needed for the second bridge placed

The Tulare Street Underpass is expected to be completed & open to traffic this summer. #BuildCA

27 1 1 0
Video

UPDATE: Hanford Viaduct |πŸ“ Kings County

Crews recently resumed placing the remaining 112 girders! This is no easy task as some of these girders can be up to 10ft tall & weigh between 95-100,000 lbs.

πŸ— Total pre-cast girders needed: 978
*Manufactured by Dragados-Flatiron Joint Venture #BuildCA

26 3 0 1